Water Run 2016

 

Cycle Start Finish Days
#1 12 - May 29 - May 17
#2 29 - May 11 - June 13
#3 11 - June 25 - June 14
#4 25 - June 09 - July 14
#5 09 - July 23 - July 14
#6 23 - July 08 - Aug. 14
#7 08 - Aug. 20 - Aug. 14

 

All allocations are subject to change upon review of storage, schedule and/or forecast information.

 


 

 Water Run 2014

Cycle Start Finish Days
#1 13 - July 07 - Aug. 25

All allocations are subject to change upon review of storage, schedule and forecast information.



Water Run 2013

Cycle Start Finish Days
#1 29 - June 16 - July 18
#2 17 - July 01 - Aug. 16

All allocations are subject to change upon review of storage, schedule and forecast information.


Water Run 2012


Cycle Start Finish Days
#1 09 - May 24 - May 16
#2 25 - May 05 - June 12
#3 06 - June 17 - June 12
#4 18 - June 29 - June 12
#5 01 - July 12 - July 12
#6 13 - July 24 - July 12
#7 25 - July 05 - Aug. 12
#8 06 - Aug. 17 - Aug. 12

All allocations are subject to change upon review of storage, schedule and forecast information.


 

Water Run 2011

As a result of the recent rainfall and wet conditions, water run will be re-scheduled to be initiated on Thursday, April 7, 2011 with water deliveries continuing thereafter.  At this time, all entitlements will be based upon five days of water usage per twenty acres running one cubic foot per second for the 100% entitlement lands prorated per entitlement category; groundwater only lands will be initially set at 25%.  All allocations are subject to change upon review of storage, schedule and forecast information.


News Release Contact:  Chris Kapheim (559) 591-0800, extension 13

 


 

Water Cycles 2011

Water Cycles are set to ensure equitable water distribution among water users. Water deliveries are rotated per cycle. Duration of cycles are set by the AID Board each year.

Water Cycles are subject to change. Contact your ditchtender for changes.
The District tracks water measurements electronically.


The 2011 Water Run Season is schedule to end on October 7, 2011

 

Updated 09-19-2011
Based on 6 days per 20 acres at 100% entitlement.

 

Cycle Start Finish Days
#1 07 - April 26 - April 20
#2 27 - April 14 - May 18
#3 15 - May 01 - June 18
#4 02 - June 19 - June 18
#5 20 - June 05 - July 16
#6 06 - July 21 - July 16
#7 22 - July 06 - Aug. 16
#8 07 - Aug. 22 - Aug. 16
#9 23 - Aug. 07 - Sept. 16
#10 08 - Sept. 23 - Sept. 16
#11 24 - Sept. 7 - Oct 14

 

Projection is subject to change.