SUBJECT TO CHANGE
Entitlement is set by the AID Board of Directors prior to the start of water run. It is set to ensure an equitable distribution of irrigation water. The entitlement for 2017 is set at 3 days for every 20 acres running 1 cfs for 100% entitlement land.
100% entitlement.......................... 3.00 days per 20 acres running 1 cfs
75% entitlement............................ 2.25 days per 20 acres running 1 cfs
50% entitlement............................ 1.50 days per 20 acres running 1 cfs
25% entitlement............................ 0.75 days per 20 acres running 1 cfs
Groundwater Only entitlement...... 0.75 days per 20 acres running 1 cfs
The 2017 volumetric water surcharge is $4.75/per acre foot;
Groundwater Only parcels are charged an additional $3.00 for a total of $7.75/per acre-foot.